SCHEDULE TO DATE
Here is what has transpired to date:
Purchase February 2nd
Demolition
Rewired house and reconfigured hall bathroom and bedroom
New panel
Redesign house and make decision to build large addition
French drain and large shotcrete on hillside
March and April
Installing new windows and going through two early permits
Build hall bathroom to completion
Rebuild old deck
Build front gate and wall
Restucco exterior of existing house
Shoring up basement and crawlspace
New main line plumbing and reconfigure kitchen
Long time working with engineer to get plans complete
Built two large fences
May and June
Start all structural work under house per plans (June 8)
Build basement bathroom
New sewer line
Removal of driveway and retaining wall
Grade and form for foundation
New trees
Water heater installation
HVAC installation
Permit approved June 22
Foundation forming inspection passed June 23
July
Build foundation and all structure in basement and garage
One week delay fixing foundation elevation
Garage walls and ceiling completed
Structural, plumbing, electrical, kitchen vaulting (major effort), two staircases
Living room windows and french doors
August
Dumbwaiter shaft and installation
Main floor framing, electrical, windows and plumbing
September
Main floor drywall and painting
One week delay between rain and roof truss debacle
Top floor structural, framing, roof, electrical, plumbing, windows and doors
Roof plywood installed and existing roof venting, flashing and paper installed
BOTTOM LINE
One month to figure out design and work on critical infrastructure issues
Two months to work on everything possible and wait for engineer
One and half months to wait for City (start working to plans)
Three months to build 1200 sq ft living area, two staircases, 200sq ft of decks, 500 sq ft of garage and exterior closets
Another month needed to get roof complete, decks waterproofed and stucco exterior
We are way ahead on painting since all doors have been painted and are ready for install